🖼️00Read later0Read More$23.5B Plutonium Plant Reuses Abandoned MOX Project at Savannah RiverEngineering News-Record·about 21 hours ago#OWTM2koG#engineeringnewsrecord#news#enr#design#nnsa+5 more🧰Tag tools✨Add tagGAO found that plutonium project at former federal nuclear weapons production site in South Carolina faced design-package delays and contractor performance issus as $3.1B in early procurement and site work advanced before baselining.15s