Squeezed between freight rail tracks and buildings—and on a site bifurcated by a busy road — a new 90,000-sq-ft maintenance facility now services Amtrak’s new Airo trains in Seattle. The $250-million maintenance and inspection facility at the King Street Coach Yard is part of the commuter railroad’s multi-billion-dollar rail yard modernization program, alongside its new trainsets.
“We are dealing with a historic amount of infrastructure improvements, specifically with the IIJA funding that we received,” said Teffin George, Amtrak senior program director, in a presentation at ENR’s Seattle Infrastructure Forum Oct. 14. “Some of the projects are really geared toward the trainsets we bought…not only for maintenance but for increased capacity.”
PCL Construction Services, Inc ., completed the 700-ft-long facility under a design-build contract, finishing in two years and $50 million under budget.…