Express Impact: Adani project stopped after Rs 227 cr wildlife fee cut to Rs 2.27 cr

The Indian Express·Chandan Haygunde·1 day ago
#Fwnd1Nm3
#indianexpress#project#forest#crore#wildlife
Reading 0:00
15s threshold

The Maharashtra Forest Department has ordered work to stop immediately at Adani Green Energy Limited ‘s 1500 MW Tarali Pump Storage Project in Patan taluka of Satara district, saying the project work started without approval from the National Board for Wildlife.

This reduction in cost to a one-hundredth matters since it proportionally reduced the money the company had to deposit for wildlife sanctuary conservation and protection to just Rs 2.27 crore instead of Rs 227 crore.

Tarali pumped storage project The figures at a glance Item Environment Clearance letter February 2025 Company’s affidavit (September 2026)

Project cost ₹5,675 crore ₹56.75 crore

4% deposit to Sahyadri Tiger Reserve ₹227 crore ₹2.275 crore

Paid so far (1% of revised cost) — ₹56.75 lakh

Why it matters

01 Adani Green Energy’s project falls in the Koyna Wildlife Sanctuary which is part of the Sahyadri Tiger Reserve.…