Menu

Michigan's Palisades Nuclear Plant Restart Date is Still Unclear
📰

Michigan's Palisades Nuclear Plant Restart Date is Still Unclear

#engineeringnewsrecord#news#enr#work#safety
Long article (560 words) — no AI summary yet.
Reading 0:00
15s threshold

Credit: Holtec International

Despite a multi-week setback related to a mishap in work by Holtec International to restart the decommissioned Palisades nuclear power plant in Michigan and regulators' concern about the site’s "chilled" safety environment, Energy Secretary Chris Wright said the 800-MW facility, closed since mid-2022, “would be back running”before year-end, possibly as early as Nov. 30. The firm did not publicly commit to a date.

Wright made the prediction at an Oct. 29 visit to the site on the eastern side of Lake Michigan. A Holtec spokesperson did not respond to ENR’s query on the prediction but the firm has said a restart will happen “when all required work is complete and all applicable U.S. Nuclear Regulatory Commission requirements and industry standards are met.”

The firm had set previous plant restart dates since recommissioning began in 2025, aided by $1.5 billion in federal funds.

Plant fuel loading was disrupted on Aug.…

Continue reading — create a free account

Join HashtagPLUS to read full articles, follow hashtags, vote, and join the conversation.