Menu

Bengaluru’s KR Puram–Silk Board Metro trial runs by October end
📰

Bengaluru’s KR Puram–Silk Board Metro trial runs by October end

The Indian Express·4 days ago
#Oe3fJnUY
#indianexpress#completed#track#works#metro
Reading 0:00
15s threshold

Trial runs on Namma Metro’s 19.75-km K R Puram–Central Silk Board stretch are expected to begin by the end of October, with construction 87 per cent complete and station entry and exit works nearing completion at 88 per cent, Bengaluru Urban Development Minister Krishna Byre Gowda said Thursday.

K R Puram-Central Silk Board, part of the Blue Line (Phase 2A) and running along a key IT and traffic-congested stretch of the Outer Ring Road, is targeted to open by mid-2027, subject to statutory clearances.

Gowda reviewed metro construction progress and directed officials to accelerate the pending work. He said system installations and preparations for testing are progressing and are likely to be operational by mid-2027.

“Blue line corridors are crucial for Bengaluru transport infrastructure. A court stay on tree felling has caused a one-year delay. Heavy traffic has also restricted construction activities to non-peak hours.…

Continue reading — create a free account

Join HashtagPLUS to read full articles, follow hashtags, vote, and join the conversation.