November 4, 2026 - 1:29 pm
Boulder City voters overwhelmingly delivered a rebuke to data centers on Tuesday.
In a ballot question , the city asked residents if data centers could be considered an acceptable use for the Eldorado Valley Transfer Area — 107,400 acres of city-owned land. Nearly 71 percent of voters voted against allowing data centers in the area, according to unofficial results on Wednesday afternoon.
However, the actual acreage where a data center could go within the transfer area is small, as 86,000 acres must be preserved for the desert tortoise and much of the available land is used by a solar farm and natural gas plant.
Throughout the country, voters almost entirely rejected data centers, with at least 38 jurisdictions passing bans or restrictions on the controversial facilities, according to The Washington Post.
Residents of the small Clark County city have been vocal about their dissatisfaction with data center development, especially after the Bureau of Land Management approved the…