Meta’s new AI-Optimized data center in El Paso
Credit: Meta
Data centre developer Applied Digital has asked tenants including Oracle and Meta for billions of dollars in guarantees before signing leases, Bloomberg reported . The money secures power for the sites, it said, citing a person familiar with the matter.
Applied Digital is also asking chipmakers Nvidia and AMD for guarantees, the person said. These are set case by case. They usually cover the cost of grid links.
Credit ratings now decide who gets space. Applied Digital has capped how much it leases to junk-rated neoclouds such as CoreWeave , Bloomberg said. That avoids the extra utility demands tied to weaker tenants.
“Applied Digital prefers to do business with investment-grade tenants, with a preferred mix of 70% investment-grade to 30% non investment-grade,” chief executive Wes Cummins said in a statement to Bloomberg.
CoreWeave told Bloomberg its partnership with Applied Digital is strong.…