MAHARASHTRA FOREST Minister Ganesh Naik Tuesday called a meeting of Adani Group executives, a day after the state Forest Department ordered work to stop immediately at Adani Green Energy Limited’s 1,500 megawatt Tarali Pump Storage Project (PSP) in Satara district’s Patan taluka, saying the project started without approval from the National Board for Wildlife (NBWL).
“The meeting was called by the minister to understand the issue and whether any mistakes have been committed,” said a state government official who did not wish to be named. He said the minister asked the company to fulfil all its obligations as per the rules and regulations for each project.
“The minister directed that if there are two different projects, then the obligation of depositing a certain amount based on project cost of each should be fulfilled without fail,” the official told The Indian Express .…