Photo courtesy Gateway Development Commission
Two tunnel boring machines at the Hudson Tunnel Project's North Bergen, N.J., launch site. The northern tube machine began excavating in October, followed by the southern tube machine in November.
The Gateway Development Commission said Nov. 18 that a second tunnel boring machine has begun excavating the southern tube of the $16-billion Hudson Tunnel Project, putting both new rail tunnel tubes under active construction in New Jersey.
The launch follows the October start of excavation on the northern tube, which has advanced approximately 400 ft and installed more than 60 precast concrete lining rings, according to GDC.
“The start of tunnel boring last month was a major milestone for the Hudson Tunnel Project, but it was only the beginning,” GDC CEO Tom Prendergast said in a statement.…