Energy
25-MW Temp Power System Bridges Grid Delay at California Manufacturing Campus
Six-building development will use 60 MWh of battery storage to supplement limited utility service until permanent upgrades are completed
By Bryan Gottlieb
Image/Copernicus Sentinel-2 Mosaic
The roughly 40-acre site of Anduril Industries' new advanced manufacturing campus is under construction adjacent to Long Beach Airport in Southern California.
October 28, 2026
ENR AT-A-GLANCE 5 Things to Know
EXPAND ↓ COLLAPSE ↑
25-MW TEMPORARY POWER SYSTEM SRG Commercial and Critical Loop are deploying bridge power so a six-building advanced manufacturing campus near Long Beach can operate before permanent utility capacity is ready.
12 MW / 60 MWh OF BATTERY STORAGE Critical Loop will distribute two battery systems at each building to supplement about 7 MW of firm Southern California Edison capacity and 2 MW of flexible service.
$1-BILLION ANDURIL CAMPUS The Information identified Anduril Industries as the tenant; its new…