Operators face longer connection waits and a growing need to bring their own electricity
Datacenter power consumption in the US is growing roughly ten times faster than grid capacity, meaning facilities may soon need to find a large chunk of their own electricity from other sources.
Surging demand for AI infrastructure is driving a wave of new server farms across America, but it is exposing long-term underinvestment in the grid networks required to deliver power where it's needed.
Insurance broker Howden calculates that datacenters would need to source up to 58 percent of their power off the grid by 2030 just to keep their share of grid capacity from growing.
Gartner warned in June that the energy consumed by AI datacenters is on track to grow 26 percent this year, and grid supply may be unable to keep pace with demand by the end of this decade.
Howden's analysis of data from the US Energy Information Administration (EIA) and S&P Global found that since the year 2000, power being fed to data…