The latest phase of the years-long Las Vegas Boulevard preservation project is nearing completion with the final phases scheduled to get underway next year.
Phase C and D of the project on the Strip between Tropicana Avenue and Russell Road started in June 2025.
Each portion of the project, which stretches between Sahara Avenue and the 215 Beltway, includes water line replacement, pedestrian crossing improvements, traffic signal upgrades, LED street lighting and smart pole installation, street repaving and median landscaping.
The project began in late 2019 with the Sahara to Spring Mountain portion.
Crews are nearing completion on the latest section of the project, with repaving continuing through Wednesday, according to Clark County construction project manager Lynette Wojtowicz.
“We have most of the utilities completed,” Wojtowicz said.…