Photo courtesy NAC ARchitecture
Malibu High School
Malibu, Calif.
Award of Merit
Submitted by: Largo Concrete
Owner: Santa Monica-Malibu Unified School District
Lead Design Firm: NAC Architecture
General Contractor: C.W. Driver
Structural Engineer: Thornton Tomasetti
Concrete Contractor: Largo Concrete
Largo Concrete’s scope on the new Malibu High School included placing thirty 14-in.-thick exposed concrete walls, the tallest at around 40 ft. Forms this tall needed engineered bracing to stand through Santa Ana winds, and they were prefabricated off site and delivered ready to erect.
Installing these walls during an excessively wet winter drove several solutions, as more than three weeks of rain delays had landed inside a 30-day window allowed by the schedule. Instead of using formwork for each wall, the team used a cycling sequence, running 15,000 sq ft of typical panels through 10 separate pours, then placing each wall in multiple lifts.…