Mumbai’s next major underground road link is moving closer to construction, with parts of two of India’s largest tunnel boring machines (TBMs), which will dig the 3.9-km twin tunnels between Malad and Kandivali, expected to arrive in the city by January 2027. The Brihanmumbai Municipal Corporation (BMC) has completed the factory acceptance test of the machines in Chennai, with tunnelling scheduled to begin by May next year.
The tunnels, which will run around 40 metres below the surface, will connect Mindspace in Malad with Charkop in Kandivali and form a crucial part of the 22.93-km Mumbai Coastal Road North project, being developed as an alternative high-speed north-south corridor between Versova and Dahisar.
The BMC has engaged Megha Engineering and Infrastructures Ltd (MEIL) to execute the tunnel works, while the machines are being manufactured by Germany-based Herrenknecht.…