Award of Merit Energy/Industrial: Pioneer Power Generation Station Phase IV
Photo courtesy Burns & McDonnell
November 9, 2026
Pioneer Power Generation Station Phase IV
Williston, N.D.
Award of Merit
Submitted by: Burns & McDonnell
Owner: Basin Electric Cooperative
Lead Design Firm/General Contractor: Burns & McDonnell
Ahead of projected load growth in the Bakken region, Basin Electric Power Cooperative needed new generation capacity online by summer 2025. Delivered on time and $10 million under budget, Pioneer Generation Station Phase IV is a 560-MW addition to Basin Electric’s existing natural gas facility. The owner chose a progressive EPC model, which allowed design and procurement to begin immediately and took months off the schedule while providing cost certainty.…