Amid severe protests against the 11,200-MW Siang Upper project in Arunachal Pradesh, the Forest Advisory Committee (FAC) of the Union Environment Ministry has recommended an in-principle forest clearance for the 1,000-MW Naying Hydroelectric Project on Siyom River, a major tributary of the Siang River.
The FAC’s recommendation for the North Eastern Electric Power Corporation Ltd (NEEPCO) project was made during its October 23 meeting, as per the official minutes of the meeting.
The Naying project is proposed to be built as a run-of-the-river project in the Shi Yomi and Siang districts, both bordering China. The estimated project cost is Rs 10,369 crore, as per submissions by NEEPCO, the project proponent.
It will entail construction of a concrete gravity dam 138 metres high from the deepest foundation level, and an underground powerhouse complex connected through a 7.08-km-long headrace tunnel.…